Step One
Dig your trench approximately16" wide and 6" deep and fill with 4" or road base material.
|
| 2 |
 |
Step Two
Compact base.
|
| 3 |
 |
Step Three
Cover road base with approximately 1" of crushed bluemetal or sand and screed to a true level.
|
| 4 |
 |
Step Four
Place units onto base with every second block and a half height. This will form the sheer bond. If the wall is higher than 2 ft an initial half block offset to the front of the wall is required.
|
| 5 |
 |
Step Five
It is essential that this first course of units is placed accurately to line and level using a sprint level. Note: Where a concrete base is used allow to harden before processing.
|
| 6 |
 |
Step Six
If an agricultural drain is required place it at the bottom of the first course with a gentle fall. Cover pipe or strip drain and surround with a free draining material.
|
| 7 |
 |
Step Seven
Backfill with a free draining material and compact. Make sure you fill the cores of the blocks as well.
|
| 8 |
 |
Step Eight
Fit cappers to wall with masonary adhesive or mortar. The back of the capper should be flush with the back edge of the rear block.
|