Interlink Wall System Installation Guide

1 Interlink Wall System Installation Guide - Step One

 Step One

Dig your trench approximately16" wide and 6" deep and fill with 4" or road base material.

2 Interlink Wall System Installation Guide - Step Two

 Step Two

Compact base.

3 Interlink Wall System Installation Guide - Step Three

 Step Three

Cover road base with approximately 1" of crushed bluemetal or sand and screed to a true level.

4 Interlink Wall System Installation Guide - Step Four

 Step Four

Place units onto base with every second block and a half height. This will form the sheer bond. If the wall is higher than 2 ft an initial half block offset to the front of the wall is required.

5 Interlink Wall System Installation Guide - Step Five

 Step Five

It is essential that this first course of units is placed accurately to line and level using a sprint level. Note: Where a concrete base is used allow to harden before processing.

6 Interlink Wall System Installation Guide - Step Six

 Step Six

If an agricultural drain is required place it at the bottom of the first course with a gentle fall. Cover pipe or strip drain and surround with a free draining material.

7 Interlink Wall System Installation Guide - Step Seven

 Step Seven

Backfill with a free draining material and compact. Make sure you fill the cores of the blocks as well.

8 Interlink Wall System Installation Guide - Step Eight

 Step Eight

Fit cappers to wall with masonary adhesive or mortar. The back of the capper should be flush with the back edge of the rear block.